Hydraulic transients in hydropower plant : Impact on power system dynamic stability
Futaleufú hydropower plant has 4 Francis turbines rated 118 MW and it is connected to the power system by 2x330 kV lines. Studies carried out in the past did not predict the instable operation of Futaleufú after a 330 kV line fault, when some Futaleufú turbines are automatically disconnected as a co...
Guardado en:
| Autores principales: | Agüero, Jorge Luis, Arnera, Patricia Liliana, Barbieri, María Beatriz, Beroqui, Mario César, Bianchi Lastra, Raúl E., Mastronardi, Jorge L. |
|---|---|
| Formato: | Objeto de conferencia Resumen |
| Lenguaje: | Inglés |
| Publicado: |
2008
|
| Materias: | |
| Acceso en línea: | http://sedici.unlp.edu.ar/handle/10915/36331 https://app.box.com/s/1ed86ffa9b80fcec2852 |
| Aporte de: |
Ejemplares similares
-
Verification by tests of models proposed for synchronous machines, excitation control systems, water supply and turbines and its control systems for colbún and machicura power plants
por: Agüero, Jorge Luis, et al.
Publicado: (2005) -
Hydropower plant models: water supply system, turbine and governor : Model validation: on site tests and grid fault simulation
por: Agüero, Jorge Luis, et al.
Publicado: (2007) -
Electromechanical oscillation damping in one hydraulic central
por: Agüero, Jorge Luis, et al.
Publicado: (1999) -
Aluminum plant : Load modeling for stability studies
por: Agüero, Jorge Luis, et al.
Publicado: (1999) -
Power system stability and control /
Publicado: (2012)